(May 8, 2025) -- Work is underway on remaining sidewalk panels and curb ramps. Up next, rebuilding the roads from the ground up. The contractor expects to complete block by block sections, beginning at 5th Street West next week. Work is weather dependent.
(May 1, 2025) -- Work is underway on remaining sidewalk panels and curb ramps. Up next, rebuilding the roads from the ground up. The contractor expects to complete block by block sections, beginning at 5th Street West the week of May 12. Work is weather dependent.
(Apr. 17, 2025) -- Work is underway on remaining sidewalk panels and curb ramps. Up next, rebuilding the roads from the ground up. The contractor expects to complete block by block sections, beginning at 5th Street West.
(Apr. 10, 2025) -- The contractor has returned to 8th Avenue West to complete the work on this project. Concrete work this week and next will be followed by paving the street.
(Apr. 3, 2025) -- The contractor expects to return to 8th Avenue West in April to complete the work on this project. A reader board was deployed on Market Street notifying residents of the return of work in April (the sign incorrectly states "8th Street" when it should read "8th Avenue", working to get that fixed).
(Mar. 20, 2025) -- The contractor expects to return to 8th Avenue West in early April to complete the work on this project.
(Mar. 14, 2025) -- The contractor expects to return to 8th Avenue West in early April to complete the work on this project.
(Feb. 11, 2025) -- The project is currently in suspension and is on track to be complete in May.
(Jan 9, 2025) -- Kirkland's contractor is working to complete surface improvements and temporary trench patch the location of the new water and sewer mains until spring. Construction will then pause, likely until at least April, but the full-street will be repaved once weather conditions allow. Asphalt is typically not installed during winter due to the product that results from poor conditions and that the asphalt plants 'shut down' as well. Project delays include unexpected site conditions, trench backfill compaction, and correcting non-compliant items. Those have been worked through and project is nearly complete.
(Nov. 7, 2024) -- Kirkland's contractor expects to grind and overlay Eighth Street West by the end of November.
(Aug. 28) --(Update: water service has been returned) There is an unscheduled water main shut down on 8thAve W from Market St to 5th St w & 5thSt W from 8thAve W to 10thAve W until Further Notice. Crews are on-site to repair the water system and will provide further information.
(April 18, 2024) -- Kirkland's capital project staff delivered Project Update flyers today and yesterday to each of the homes that will benefit from the City's water and sewer main upgrade along Eighth Avenue West and Fifth Street West.
Kirkland's contractor is planning on April 29 to begin begin construction.