(Apr. 10, 2025) -- Construction is progressing quickly at both locations, downtown on Central Way from Market Street to Main Street and on NE 124th Street near the North Kirkland Community Center.
Parking on Central Way will be restricted from 6 a.m. to 5 p.m. (Monday to Friday). There will be intermittent closures of the crosswalks as they are being updated. Pedestrian detours will be in place during those crosswalk closures.
(Apr. 3, 2025) -- Construction is progressing quickly at both locations, downtown on Central Way from Market Street to Main Street and on NE 124th Street near the North Kirkland Community Center.
Parking on Central Way will be restricted from 6 a.m. to 5 p.m. (Monday to Friday). There will be intermittent closures of the crosswalks as they are being updated. Pedestrian detours will be in place during those crosswalk closures.
(Mar. 27, 2025) -- Construction is progressing on the two HAWK signals on NE 124th Street near the North Kirkland Community Center and Park. The signal poles are being built at the first locations in Kirkland for HAWK signals. There will be intermittent closures of the crosswalks as they are being updated, pedestrian detours will be in place during those closures.
Work also began downtown on Central Way this week from Market Street to Main Street. Parking on Central Way will be restricted when the contractor is working on the medians between 9 a.m. and 3 p.m. There will be intermittent closures of the crosswalks as they are being updated, pedestrian detours will be in place during those closures.
(Mar. 17, 2025) --Construction is progressing on the two HAWK signals on NE 124th Street near the North Kirkland Community Center and Park. Work is expected to begin on Central Way downtown on Wednesday, March 17. Parking on Central Way will be restricted when the contractor is working on the medians between 9 a.m. and 3 p.m. There will be intermittent closures of the crosswalks as they are being updated, pedestrian detours will be in place during those closures.
(Mar. 14, 2025) --Construction has begun for the HAWK signals on NE 124th Street near the North Kirkland Community Center and Park. Work is expected to begin on Central Way downtown in late-March. Parking on Central Way will be restricted when the contractor is working on the medians between 9 a.m. and 3 p.m. There will be intermittent closures of the crosswalks as they are being updated, pedestrian detours will be in place during those closures.
(Feb. 28, 2025) -- Construction mobilization has begun for the HAWK signals on NE 124th Street near the North Kirkland Community Center and Park. Work is expected on Central Way downtown in a few weeks.
(Jan. 22, 2025)-- Construction is expected to begin on Monday, February 3 on NE 124th Street.