(April 24) -- This project is waiting on PSE to provide power to the crossing lights.
(April 14) -- For the project to progress the City is waiting on PSE to complete their tasks to provide power to the equipment. The crosswalk is functional and temporary flags have been added for pedestrian visibility.
(April 2) -- Work is progressing well on this sidewalk/crosswalk project.
(March 19) -- Crews will be forming/pouring the center island median curb's into next week.
(March 12) -- Curb and gutter are poured, center island median work expected next week.
(February 26) - Drivers can expect the traffic control to shift the southbound lane into the center lane.
(February 19) -- Work underway on this sidewalk and crosswalk project in north Kirkland.