Update (May 30, 2024) -- The 2024 Street Preservation Program will begin construction on August 5th, on Northeast 132nd Street. The contractor will rebuild 20 curb ramps, lower utilities, and overlay from 100th Avenue Northeast to 112th Avenue Northeast.
The following streets will also be overlayed.
- Northeast 139th Street, from Northeast 140th Street to 97th Avenue Northeast
- Northeast 140th Street, from 93rd Avenue Northeast to its street-end
Additionally, Lakeside Industries will also build a raised crosswalk at O.O. Denny Park across Holmes Point Drive. This improved crossing compliments the two speed cushions installed last fall.