(Apr. 10, 2025)-- Outreach staff are working on a social media push for public notification of this project. Project video coming soon...
(Apr. 3, 2025)--This project was presented to the Downtown Merchant's meeting of the Kirkland Downtown Association on Tuesday, April 1. Outreach staff are working on a social media push for public notification of this project.
(Mar. 20, 2025) --The construction contract was awarded by City Council on Tuesday, March 18. City staff will begin the contracting and administrative pre-construction process.
(Mar. 6, 2025) --This project bid is headed to City Council on Tuesday, March 18. If council approves the contract award memo, City staff will begin the contracting and administrative pre-construction process.
(Feb. 27, 2025) -- This project was presented to the Transportation Commission at it's 2/26/25 meeting and the Kirkland Rotary at it's 2/24/25 meeting.
(Feb. 2025) -- The construction contract is headed to City Council for award. Construction is expected to begin this spring.
(Nov. 7, 2024) -- This project is expected to go "out to bid" in January for 2025-2026 construction.
(Feb. 27, 2024) -- The timeline for the Northeast 85th Street multi-modal path is undetermined, at this point, pending funding.