(October 29) - Grinding was completed this week, paving is scheduled for early next week.
(October 22) -- Work continues on the north side of NE 128th Street this week and next. If the weather holds we expect nighttime grinding and paving of the street on Wednesday, October 26 and Thursday, October 29.
(October 15) -- Construction has shifted to Phase 3, and the transit center is expected to open by end of day Friday, October 16. See new phase 3 map on this page for traffic direction and pedestrian changes.
(October 8) -- No changes to the work zone are expected this week, but by mid-week next week we expect the shift to happen and prohibit westbound travel, opening up eastbound travel to vehicles from 120th Avenue NE.
(October 1) -- Work continues on NE 128th Street. It's possible that work will shift work to the north half of the street late next week, which would close westbound vehicle travel and open eastbound travel. Follow on-site detours and directions.
(September 24) -- Work continues this week on eastbound NE 128th Street. The entrance to the DeYoung Pavilion from NE 128th Street will be open from 6:00 a.m. to 7:30 p.m. Additional work on curb ramps is occurring on NE 130th Place and 124th Avenue NE. Please follow pedestrian and vehicle detours.
(September 17) -- Drivers can expect a change in traffic flow at this location, as westbound travel of Northeast 128th Street is expected to be reopened at Evergreen Hospital. Eastbound travel remains closed from 120th Avenue Northeast to 124th Avenue Northeast (see phase 2 map). King County Metro has relocated the transit center during this closure. Metro users should follow their signage for bus stop changes. Kirkland’s contractor continues the concrete work for the intersection to the transit center entrance. Additional ramp repairs are beginning around the hospital campus to facilitate the coming street overlay of Northeast 130th Lane.
(September 10) -- The phase 1 closure is on schedule. Work continues on the closed section of NE 128th Street between Evergreen Hospital and the DeYoung pavilion.
(September 3) -- Work is underway and NE 128th Street is closed from 120th Avenue NE up to the northern DeYoung Pavilion driveway. The concrete intersection is expected to be poured next week and will remain closed into the following week for curing and surface preparation (relief joint saw cutting, temporary pavement markings, etc.)
(August 27) -- NE 128th Street will be closed for three weeks beginning Monday, August 31. Patients and visitors should plan for extra time to reach their destinations at Evergreen Hospital.