(May 8, 2025) -- Reed Excavating is planning on May 12 to pave a base layer of asphalt along 124th Avenue Northeast's northbound lane, between Northeast 116th and 124th streets.
The contractor will use lane-shifts to keep travels lanes open in both directions.
Reed Excavating will close for up to two hours business' driveways along the northbound lane.
Later in mid-June, however, Reed Excavating is planning to close the entire roadway for a day so its crews can apply the final layer of asphalt along the same section of 124th Avenue Northeast.
The 7 a.m. to 7 p.m. closure will allow the contractor to pave the roadway with one, continuous mat, devoid of cold joints that can undermine the street's structural integrity.
Kirkland's staff will post the detour route to this page when it becomes available.
Updates to this page are posted every Thursday.