(April 24, 2025) -- SCI Infrastructure is planning on May 12 to pave a base layer of asphalt along 124th Avenue Northeast's northbound lane, between Northeast 116th and 124th streets.
The contractor will use lane-shifts to keep travels lanes open in both directions.
Later in May or early in June, however, SCI Infrastructure is planning to close the entire roadway for a day so its crews can apply the final layer of asphalt along the same section of 124th Avenue Northeast.
The 7 a.m. to 7 p.m. closure will allow the contractor to pave the roadway with one, continuous mat, devoid of cold joints that can undermine the street's structural integrity.
Kirkland's staff will post the detour route to this page when it becomes available.
Updates to this page are posted every Thursday.