(September 11, 2025) -- Work on sewer joints is expected to begin the week of September 15. The existing sewer line was inspected and more locations will receive spot repairs in advance of the UV sewer lining.
(September 4, 2025) -- Work is expected to begin as early as next week on spot repairs on at least three locations on 10th Avenue West. Project Update mailing is expected to be sent next week.
(August 28, 2025) -- No update this week.
(August 14, 2025) -- The contractor will video the existing sewer line to ensure there are not blockages or offsets that need additional repair. There are three known locations that they will have to open to repair before they can line the pipe. Project mailer will be sent in the coming weeks detailing the project.
(August 7, 2025) -- A preconstruction meeting for this project occurred this week. Work is expected to begin in mid-August.
(July 31, 2025) -- No update to previous information.
(July 25, 2025) -- The pre-construction meeting is scheduled for early August and construction is expected following that meeting.
(July 17, 2025) -- No update to the previous information.
(July 3, 2025) -- This project is expected to begin in late-July/August. There is minimal impact expected to traffic or the sewer system, as small holes are dug at intervals on the sewer pipe on 10th Avenue to guide the pipe liner. This is a pilot program to see if the smaller sewer pipes can be lined for the much larger West of Market Sewer System project in 2026.
(June 20, 2025) -- No update this week.
(June 12, 2025) -- No schedule updates. Staff will begin community outreach for 10th Avenue West in July.
(May 29) -- The lead time for the lining product has been determined at approximately 2 months. Construction now expected to begin late July.
(May 22, 2025) -- This project is headed to construction, expected to begin in early June. Residents will be notified via mail and project signs.