November 12 -- Flowline is planning on Monday to close a 150-foot section of Northeast 120th Street, west of 108th Avenue Northeast.
The closure will begin at 7 a.m. and continue until 4 p.m. The entire street will be accessible after 4 p.m. until 7 a.m. However, during work hours of the 12-day closure, the contractor re-open sections of the trench that it had covered with steel plates to continue the stormwater upgrade.
The contractor will begin at the bottom of the hill--the street's western-most end. It plans to open 100 to 150 feet of trench per day.
November 5 -- Work is underway. The contractor expects to need to close the road during working hours when the open the street to install the stormwater pipe. Local residents will be notified with an updated project update.
October 22 -- Work now expected to begin Monday, October 26. Tree removal is expected to be one of the first tasks of the project.
October 15 -- Work begins Monday, October 19.
October 10 -- Work is expected to begin October 19. Project Update mailer was sent to the post office today for nearby addresses.
September 24 -- Work is expected to begin in early October on this project.
July 22, 2026 -- Construction contract award is headed to Kirkland City Council. Work is expected to begin in August/September.