(May 31) -- Work is expected overnight Saturday, beginning at 8:00 p.m. on June 3 and ending by 8:00 a.m. on Sunday, June 4. Next week, workers will begin subgrade preparation in advance of final paving. Night work is from 8:00 p.m. to 5:00 a.m., Monday night to Friday morning.
(May 15) -- Work will resume in June when the contractor returns to overlay the intersection and 116th Avenue Northeast. Work is currently delayed due to a fiber-optic line that requires specialty splicing.
(April 26) -- Crews are pouring sidewalks, and are expected to be finished with concrete work on Friday, April 27. During the weeks of May 1 and 8, crews will return to night work.
(April 17) -- Construction has resumed and this project is expected to be complete this spring.
(April 5) -- Construction will resume on April 10, with the contractor working from 8:00 p.m. to 5:00 a.m. from April 10 to April 14.
(Mar 23) -- Franchise utilities (PSE, Comcast, Ziply) are scheduled to relocate their facilities so that the project can resume construction. Construction is expected to resume on April 10, but is dependent on the franchise utility work being completed.
(Jan 16) -- This project is in suspension and is expected to resume in four to six weeks.
(Dec 15) -- Work continues, with the contractor recently installing the pole for the new signal. The contractor plans to work through Dec. 22, returning after the holidays to continue construction.
(Nov 4) -- This project is alternating between day and night shift, returning to nights the week of November 7. The contractor is working to fill potholes near the intersection, and planning the concrete pours of curb/gutter and sidewalk on 116th Avenue NE and NE 124th Street. The driveway for the Starbucks is expected to reopen by November 11.
(Sept 1) -- This project will resume as soon as a franchise utility conflict that is in the critical pathway is cleared. At this time it's expected to resume either September 11 or September 18.
(Aug. 26) -- The contractor Kirkland hired to create a right-turn lane at 116th Avenue Northeast's intersection with Northeast 124th Street expects to resume work on Sept. 6.
(Jul 21) -- This project is currently suspended while the contractor awaits a City of Kirkland franchise utility to complete work moving their underground utility. Work is expected to resume mid-August.
(Apr 10) -- Work begins tonight on the new right turn lane. Work hours are 8 p.m. to 5 a.m., beginning Sunday night and finishing Friday morning. Please drive safely through this night construction zone.
(Mar. 15) -- We've had the preconstruction meeting and received the contractors proposed work schedule. Currently we expect the work to begin on April 3, but the start date has still not been settled.
(Feb. 7) -- Construction is expected to begin in early March. Work for the project will occur overnight, between 8 p.m. and 5 a.m. Please drive carefully through the intersection.
(Dec. 15) -- City Council awarded the construction contract to Interwest Construction(PDF, 2MB) at it's December 14, 2021 meeting. Construction expected to begin this winter.