NM-0051 Rose Hill Business District Sidewalks
- Complete continuous sidewalks on both sides of NE 85th Street between 120th Avenue NE and 132nd Avenue NE
- Complete continuous sidewalk on both sides of 124th Avenue between NE 80th Street and NE 90th Street
- Install landscape strips with trees, pedestrian lighting and street lighting on both sides of NE 85th Street
- Install landscaped channelized islands at two or three locations along the corridor
- Consolidate driveways, eliminate driveways and/or modify driveways, where possible, to meet city and state standards and to increase safety
TR-0078 NE 85th Street/132nd Avenue NE Intersection Improvements
- Add a northbound 132nd Avenue to eastbound NE 85th Street right turn lane.
- Re-stripe the southbound to eastbound left turn lane to increase vehicle storage length.
TR-0079 NE 85th Street/114th Avenue NE Intersection Improvements
- Install an additional southbound 114th Avenue NE to eastbound NE 85th Street left turn lane.
- Transition traffic lanes into existing southbound I-405 on-ramp carpool lane.
TR-0080 NE 85th Street/124th Avenue NE Intersection Improvements
- Add an channelization island for future eastbound NE 85th Street to northbound 124th Avenue NE left turn lane.
ST-0075 NE 85th Street Utility Underground Conversion
- Convert aerial utility lines to underground systems along NE 85th Street from 120th to 128th Avenue NE.
- Install conduit underground for future utility conversion from 128th Avenue NE to 132nd Avenue NE.
SD-0025 NE 85th Street Detention/Sediment Control
- Provide water quality treatment for surface water within the 85th Street sub-basin from approximately 126th Avenue to 132nd Avenue NE (not currently treated to existing standards).