NE 85 St Improvements

 |
• Reduce traffic congestion |
| • Enhance the pedestrian experience |
| • Provide continuous sidewalk facilities |
• Stimulate economic vitality and redevelopment |
|
Join the 85th Street Project List-Serve and Automatically Receive E-mail Updates... If you would like to receive electronic notices of upcoming meetings regarding the projects, please click here to sign-up.
 |
January 20, 2012 Update: Signal Video Detection and NE 85th Street/114th Avenue Intersection Improvements are complete. Underground utility wire conversion has been rescheduled to start in early February, 2012. See December 2011 newsletter ( 1,705KB). Project Overview: The NE 85th Street Corridor Improvements are a direct result of a collaborative community planning effort with the Rose Hill Business District businesses, property owners, neighborhood residents, Sound Transit, and the City of Kirkland. The improvements provide a series of coordinated streetscape facilities to minimize traffic delays; enable pedestrians, drivers, bicyclists, transit riders and others to have a safe and pleasant experience; and, to develop a comprehensive transportation system to stimulate economic vitality and redevelopment. The projects include:
Underground Powerlines:
- Convert aerial utility lines to underground system along NE 85th Street from 120th to 128th Avenue NE
- Install conduit underground for future utility conversion along NE 85th Street from 128th Avenue NE to 132nd Avenue NE
Sidewalks:
- Complete sidewalk on both sides of 124th Avenue NE between NE 80th Street and NE 90th Street
- Complete sidewalk on both sides of NE 85th Street between 120th Avenue NE and 132nd Avenue NE
- Install landscape strips with trees, pedestrian lighting and street lighting on both sides of NE 85th Street
Intersections:
- Add Intelligent Transportation System elements at each signalized intersection to coordinate signal timing along the corridor and create a pathway for connection to future Traffic Control Center
- Install additional southbound 114th Avenue NE to eastbound NE 85th Street left turn lane
- Install channelization island for future eastbound NE 85th Street to northbound 124th Avenue NE left turn lane
- Add northbound 132nd Avenue to eastbound NE 85th Street right turn lane
- Re-stripe southbound to eastbound left turn lane to increase vehicle storage length
Detention/Sediment Control:
- Provide water quality treatment for surface water within NE 85th Street sub-basin from approximately 126th Avenue to 132nd Avenue NE
Street Resurfacing:
- Resurface NE 85th Street Corridor
When: The planned schedule may change and will be updated regularly.
|
Construction Phase |
Construction Start |
Substantial Completion |
| 114th/85th Intersection |
Complete |
Complete |
|
Sidewalks on 124th |
Spring 2012 |
Fall 2012 |
| Utility Underground Conversion |
February 2012 |
Summer 2013 |
| 124th & 132nd Intersection |
Winter 2012 |
Summer 2013 |
| Sidewalks on 85th |
Winter 2012 |
Winter 2013 |
| Street Resurface |
Winter 2013 |
Winter 2013 |
How can I stay informed?
Send in a comment or question.
Join the 85th Street Project List-Serve and Automatically Receive E-mail Updates... If you would like to receive electronic notices of upcoming meetings regarding the projects, please click here to sign-up.