2014 Projects

City Council approved the 2014 Neighborhood Safety Projects on June 17, 2014.
June 17 Council Memo (PDF-1.2 MB)

2014 Applications 2014 Project Map (PDF-488 kb)

2014 Funded Projects:

Rapid Flashing Beacon | Project: 14NSP01
2014 NSP Project 1 14NSP01 After
Location: NE 132nd Street at 121st Ave NE (relocation of crosswalk to east side of intersection, add rapid flashing beacon, and add east bound to north bound turn lane)
Neighborhood: Evergreen Hill | Project Manager: Johanna Palmer | City Staff: Kari Page
Project completion: Complete

Rapid Flashing Beacon | Project: 14NSP02
2014 NSP Project 2
Location: Juanita Drive Trail Crossing at NE 137th Street connecting Big Finn Hill Park
Neighborhood: Finn Hill | Project Manager: Scott Morris | City Staff: Kari Page
Project completion: Pending state grant authorization and design. Anticipated completion in 2017.

Crosswalk and curb  | Project: 14NSP03
2014 NSP Project 3 
Location: Along 84th Ave NE from NE 139th Street to NE 141st Street
Neighborhood: Finn Hill | Project Manager: Jon Pascal | City Staff: Kari Page
Project completion: Complete

Rapid Flashing Beacon | Project: 14NSP04
2014 NSP Project 4 14NSP04 After
Location: 132nd Street NE at 105th Ave NE
Neighborhood: Juanita | Project Manager: Ken Albinger | City Staff: Kari Page
Project completion: Complete

Trail Connection | Project: 14NSP05
2014 NSP Project 5
Location: South side of Forbes Creek Drive between 113th Court NE and 115th Court NE to Cross Kirkland Corridor
Neighborhood: Juanita | Project Manager: Ken Albinger | City Staff: Kari Page
Project completion: Pending easement negotiation with private property owner. Anticipated completion in 2016.

Crosswalks and Street Lights | Project: 14NSP06
 14NSP06 Before  14NSP06 After 
Location: Along 90th Ave NE at NE 134th Street and NE 139th Street (adding street lights that are warranted by lighting study).
Neighborhood: Finn Hill | Project Manager: Jon Pascal | City Staff: Kari Page
Project completion: Complete

Crosswalks | Project: 14NSP07
Project 14NSP07 Before  Project 14NSP07 After
Location: Along NE 145th Street at 88th Ave NE and 92nd Ave NE
Neighborhood: Finn Hill | Project Manager: Scott Morris | City Staff: Kari Page
Project completion: Complete